Procurement, Installation and O&M of Water Meters in Lahore

Project Description

Water conservation has become one of the paramount concerns for Pakistan, as the water table is depleting with every passing day due to massive extraction and a rapidly increasing population. In the absence of water meters at the production, distribution, and consumer ends, the quantity of water produced, supplied, and lost cannot be accurately measured. There is a dire need to establish a correlation between the volume of water produced and the volume of water sold through proper water metering. Without water meters, it is impossible to accurately estimate the supply and demand of water resources. Implementing water metering will help reduce water losses, ease stress on the aquifer, and potentially prevent excessive pumping and extraction of groundwater.

Salient Features

Project Cost: PKR 9.3 Billion
Proposal Type: Solicited with BOT
Concession Period: 10 Years (excluding installation period)
Total Meters: 711,265
Sector: Water Supply and Sanitation
Potential Impact: The project is expected to conserve water resources, slow the declining rate of the groundwater table and reduce water losses.
Executing Agency: Water and Sanitation Agency (WASA), Lahore

 

Objectives

  • Improving collection levels
  • Minimize illegal connections and water theft
  • Minimizing non-revenue water
  • Conservation of water
  • Minimizing water pumping cost

 

Current Status:

 

  • Concession Agreement signed on 14-03-2022
  • Financial Close achieved on 30-11-2022
Private Party:

Consortium of

  1. M/s Wenling Younio Water Meter Co. Ltd.
  2. M/s Jiangsu Xinlang Environmental Company (Private) Ltd.
  3. M/s China Energy Engineering Group Jiangsu No.3 Electric Power Construction Co. Ltd.
Special Purpose Vehicle titled, “XINLANG Lahore Water Metering (SMC-Private) Limited” registered with SECP